Energy Centre Parking Garage

Project Information

  • Owner Shorenstein Realty
  • Design Eskew+Dumez+Ripple
  • Size 155,000 Square Feet
  • Budget $4,900,000
  • Completion August 2002

Located at 600 Loyola Avenue, the Energy Centre Parking Garage was a project completed in two phases. The first phase included the demolition of several existing buildings and parking lots. The second phase was the construction of a four level (155,000 square foot) structure.

The project began in May, 2001, and continued until August, 2002. In order to save time, the design team of Eskew+Dumez+Ripple, along with Woodward Design+Build’s input, decided to construct the garage utilizing a pre-cast concrete structure, which proved to be very conducive to the time and site conditions.

The garage is wrapped with architectural pre-cast and with a decorative Trellis at the ground level. The garage has 461 new parking spaces and an area on the ground level for future retail space that will face Lafayette Mall Street, which runs between the existing building and the new garage.

Branding and website development by Zande+Newman Design